PROJECTS
Our scope :
Engineer Supply, install, commissioning and startup as follows:
-
Low voltage main switchgear for 2 Pump Stations BPS3, and BPS4
-
Motor Control Center and variable Speed Drive for 2 pump Stations BPS3, and BPS4.
-
Low voltage switchgear for all auxiliary power supply for BPS3 BPS4
-
Bust Duct system 5000 A and 3200 A between Main LV switchgear and Transforms
-
Supply and laying Cables, cable tray between Low Voltage switchgear, MCC, VSD and Electrical Motors.
-
Install all SCADA, panels RTU instrumentation, etc.
-
Install pumps, and motors, pipe work valves etc.
-
Install overhead crane for both pump stations BPS 3 and BPS 4 ( 7.5 ton amd 6 Ton)
Tender No. : 141/2005
Contract Value : 1,369,000.000 R.O
Client : Public Authority for Electricity and Water
Consultant : NJS Consultants form (Samail to IZKI)
Energoprojekt Entel LLC ( IZKI to Nezwa)
Main Contractor : ERKO Oman LLC